Single or three phase temporary overhead supply
Who is this for?
For builders and trades to work when there is no permanent connection to the site.
How long will it take?
5-6 business days* in the Perth metro and major regional towns.
10-11 business days* in country and rural areas.
*your completed application has been accepted and your customer project or online application reference number is supplied. (as per accordance with WASIR cl. 12.2.1.2 (1.) and 12.2.1.3.)
How much will it cost?
$570
A registered electrical contractor will need to submit this application.
Temporary power supply allows builders and trades to work when there is no permanent connection to the site. To set up an account for temporary electrical supply, contact your retailer and then refer to the options below.
What to include with your application
Retailer reference number
After applying for a new installation with your electricity retailer, you’ll be provided with a retailer reference number for your application. You’ll need a Retailer Reference Number for each new meter to be connected.
Project application reference number
Your customer project or online application reference number. (As per accordance with WASIR cl. 12.2.1.2 (1.) and 12.2.1.3.)
Notice of completion number
Building and Energy will provide a completion number after you've lodged that the work for the new installation has been completed through eNotice.
Neighbours authority
If your project will impact your neighbour’s property by having new assets installed or relocated on or in front of their property, you’ll need their authorisation.
Ready to apply for a temporary overhead supply?
Once you’ve gotten the above, you are ready to apply. Estimated time to complete: 10 minutes