Large scale relocation

share icon

Who is this for?

For people wanting to relocate or permanently remove large portions of equipment not covered by smaller services.

*This is for distribution assets only, if your request also includes transmission and/or communication infrastructure (this includes stay poles to transmission lines), use Move or remove transmission and communication assets.

clock icon

How long will it take?

3 months to provide you with a technical assessment

8-12 months to provide you with a design and quote, depending on the complexity of your project

3 months to construct, upon payment of quote and confirmation your site is ready

Timeframes indicative only and subject to change based on demand.

dollar icon

How much will it cost?

We'll provide a quote after we complete the scoping and design of your project.

Application fee

Application fee (plus 0.59% credit card surcharge) $497.42

 

Design fee

Project complexity Fee
Standard $1,320
Detailed $3,300
Complex $6,600

* While the design fee is GST inclusive, the GST exclusive amount will be deducted from the access offer if proceeding, i.e. GST is not refunded

 

Other fees

Description Fee
Construction costs We will provide a quote
Cancellation fee $550

The cost of an electricity supply is dependent on how much power you require. In most cases, the cost will be based on what we call the Distribution Low Voltage Connection Scheme.

 

This service covers a wide range of possibilities, if you are unsure about how to proceed, please consider beginning with a feasibility study.

Application process

Completed application and project information is required to commence design.

You’ve applied
1

We’ll contact you to discuss your application.

You’ll receive a scope
2

After our technical assessment we’ll confirm the scope of works with you.

You’ll receive design fee invoice
3

Once payment is received, we will design the project to your needs.

You’ll receive a quote for the delivery of the works
4

After the acceptance and payment is received, we’ll schedule the works for delivery. Schedules are dependent on your location and the complexity of our work.

Let us know how we went
5

Your feedback is important to help ensure we’re meeting your needs and expectations.

Additional information you need to know

If you’re application is in relation to subdividing your land, there are a few conditions you need to meet before you can request clearance from the Western Australian Planning Commission (WAPC) or complete your built strata development. If we have asked you to apply for a new connection in order to meet our condition(s), it’s handy for us to know if it’s linked to a subdivision so we can collate all the right information to ensure the right checks and balances are undertaken.

What to include with your application

circle check orange

Authority to Act

If you are not the Landowner, you must provide a signed letter from the Landowner(s) confirming that you have authority to act on their behalf. The letter must include the following: 

  • Full name of the Landowner(s) as per Landgate records
  • Your full name 
  • Your role in relation to the project
  • A clear statement authorising you to act on the Landowner’s behalf
  • Date (must be no more than 12 months from application submission date)
  • Signature of the Landowner(s) - (handwritten or digital signatures are acceptable) 

 

Applications will not be accepted without this letter. 

circle check orange

A site plan – PDF

Provides us with an understanding of your work site, the location of existing and new assets and help us to design your product. It will need to include:

  • your property
  • neighbouring properties
  • the location of the supply point
circle check orange

A CAD site plan

Your CAD plan helps us better understand your work site and location of assets. We extract data from your plan to assist us with your design.

 

Please submit:

  • Your CAD site plan in DGN format with MGA94 Zone 50 coordinates and reference files
circle check orange

Site photos

Help us understand your current connection arrangements and more easily identify potential site-specific issues. Photos will need to include:

  • The extent of the worksite
  • Any obstructions in the area
circle check orange

Neighbour's authority

If your project will impact your neighbour’s property by having new assets installed or relocated on or in front of their property, you’ll need to provide an email or letter from them confirming their authorisation. 

circle check orange

Western Australian Planning Commission (WAPC) approval letter (if applicable)

This ensures we only design and construct electrical infrastructure for developments formally approved and aligned with State planning requirements.

 

Applications will not be accepted without this letter. 

Ready for a large-scale relocation?

Once you’ve gotten the above, you are ready to apply.

FAQs