Distribution isolation (LV/HV)
Who is this for?
You are doing work that requires part of the Western Power electricity distribution network (0 – 33,000 volts) to be isolated.
How long will it take?
3 months to provide you with a technical assessment
4 -6 months to provide you with a design and quote, depending on the complexity of your project
3 months to construct, upon payment of quote and confirmation your site is ready
How much will it cost?
We'll provide a quote after we complete the scoping and design of your project.
Application fee
Application fee (plus 0.59% credit card surcharge) | $497.42 |
Design fee
Project complexity | Fee |
---|---|
Standard | $1,320 |
Detailed | $3,300 |
Complex | $6,600 |
* While the design fee is GST inclusive, the GST exclusive amount will be deducted from the access offer if proceeding, i.e. GST is not refunded
Other fees
Description | Fee |
---|---|
Construction costs | We will provide a quote |
Cancellation fee | $550 |
The cost of an electricity supply is dependent on how much power you require. In most cases, the cost will be based on what we call the Distribution Low Voltage Connection Scheme.
Application process
You’ve applied
1
You’ll receive a scope
2
You’ll receive design fee invoice
3
You’ll receive and access quote
4
After the acceptance and payment is received, we’ll schedule the works for delivery.
5
What to include with your application
A site plan
Provides us with an understanding of your work site, the location of existing and new assets and help us to design your product. It will need to include:
- Your property
- Neighbouring properties
- The location of the supply point
Single line diagram (SLD)
A single line diagram (SLD) provides us with the technical information to design a connection to meet your requirements. The SLD must include:
- Point of supply details – such as pillar, pole, sole use, district transformer etc.
- Size of consumer mains, with clear labels for ‘New’ or ’Existing’
- Service Protection Device (SPD) setting - this must match the total maximum demand in the Load Breakdown Schedule and application form.
- Metering arrangement with clear labels for ‘New' or 'Existing' and meter numbers for existing meters.
Authority to Act
If you are not the Landowner, you must provide a signed letter from the Landowner(s) confirming that you have authority to act on their behalf. The letter must include the following:
- Full name of the Landowner(s) as per Landgate records
- Your full name
- Your role in relation to the project
- A clear statement authorising you to act on the Landowner’s behalf
- Date (must be no more than 12 months from application submission date)
- Signature of the Landowner(s) - (handwritten or digital signatures are acceptable)
Applications will not be accepted without this letter.
Ready to apply for a distribution isolation?
Once you’ve gotten the above, you are ready to apply. Estimated time to complete: 10 minutes
FAQs
You will be charged a design fee upon lodging your application.
Once your project proceeds to construction phase the design fee, excluding GST, is deducted from the price on your Access Offer and Acceptance.
Sometimes your circumstances change and you may need to cancel or change the information within your application after you have submitted it to us.
If you wish to change the scope of work in your application we will first review the change and then either:
- continue the project with the variation and invoice you for any additional materials, design work and remobilisation costs incurred. We will typically only take this approach when the change is very minor.
or
- if the change is significant we will cancel your project. You will need to submit a new application with your new requirements.
For cancelled applications we will invoice you for the costs incurred up to the point of cancellation (time and materials). If construction work has already commenced we will refund the difference from your access offer less any costs incurred.