Increase residential supply

share icon

Who is this for?

For people wanting to increase the electricity supply to your residential property.

clock icon

How long will it take?

3 months to provide you with a technical assessment.

4-6 months to provide you with a design and quote, depending on the complexity of your project.

Timeframes indicative only and subject to change based on demand.

dollar icon

How much will it cost?

We'll provide a quote after we complete the scoping and design of your project.

Application fee

Application fee (plus 0.59% credit card surcharge) $497.42

Design fee

Project complexity Fee
Standard $1,320
Detailed $3,300
Complex $6,600

* While the design fee is GST inclusive, the GST exclusive amount will be deducted from the access offer if proceeding, i.e. GST is not refunded

Other fees

Description Fee
Construction costs We will provide a quote
Cancellation fee $550

The cost of an electricity supply is dependent on how much power you require. In most cases, the cost will be based on what we call the Distribution Low Voltage Connection Scheme.

Application process

You’ve applied
1

We’ll contact you to discuss your application.

You’ll receive a scope
2

After our technical assessment we’ll confirm the scope of works with you.

You’ll receive design fee invoice
3

Once payment is received, we will design the project to your needs.

You’ll receive a quote for the delivery of the works
4

After the acceptance and payment is received, we’ll schedule the works for delivery. Schedules are dependent on your location and the complexity of our work.

Let us know how we went
5

Your feedback is importance to help ensure we’re meeting your needs and expectations.

Additional information you need to know

If you’re application is in relation to subdividing your land, there are a few conditions you need to meet before you can request clearance from the Western Australian Planning Commission (WAPC) or complete your built strata development. If we have asked you to apply for a new connection in order to meet our condition(s), it’s handy for us to know if it’s linked to a subdivision so we can collate all the right information to ensure the right checks and balances are undertaken.


 

What to include with your application

circle check orange

Permission from your strata company (if applicable)

Before applying to upgrade your connection, strata lot owners should first seek permission from their strata company to use an allocation of the total network capacity allocated to the strata scheme.

Ready to increase your residential supply?

Once you’ve gotten the above, you are ready to apply.