You've applied
We’ll contact you within 10 days to discuss your application and confirm your required dates.
We'll provide a quote
after we complete the scoping and design of your project.
Application fee (plus 0.59% credit card surcharge) | $497.42 |
Standard | $1,320 |
Detailed | $3,300 |
Complex | $6,600 |
* While the design fee is GST inclusive, the GST exclusive amount will be deducted from the access offer if proceeding, i.e. GST is not refunded
Construction costs | We will provide a quote |
Cancellation fee | $550 |
The cost of an electricity supply is dependent on how much power you require. In most cases, the cost will be based on what we call the Distribution Low Voltage Connection Scheme.
Up to 10 business days
to respond to your application.
After our technical assessment
we’ll contact you to discuss your requirements and work with you on an expected delivery date in line with the complexity of your project.
Due to the current economic conditions, we are experiencing a high volume of distribution grid connection and relocation applications as well as seeing the delivery timeframes for some materials items significantly extended. This has resulted in longer timeframes for products and services.
This is for connecting power to a property where there has never been a connection to the Western Power network before. If you simply need to reconnect an existing connection, then please speak to your retailer to set up a new account.
Your CAD plan helps us better understand your work site and location of assets. We extract data from your plan to assist us with your design.
For a pillar site plan to be accepted, it must clearly show:
In order to provide a fast, accurate quote and advice on your new connection arrangement we require a comprehensive site plan with details of your current and/or proposed site layout. This includes but is not limited to the following information being clearly marked on your plan:
The pillar needs to have an exclusion zone of 50cm from its centre. Inside or under the exclusion zone there must not be any:
Find out what underground assets may be in the vicinity by submitting a Dial Before You Dig application.
An easy way to create a site plan is to use a online mapping service like Google Maps. Just take a screen shot of the address and then label the requirements on it.
If you’ve got access to construction plans or engineering drawings, you’ll be able to submit these as a site plan as long as it includes all our requirements.
Help us understand your current connection arrangements and more easily identify potential site specific issues. Photos will need to include:
Site photos help us understand your current connection arrangements and more easily identify potential site specific issues. If you’re able to supply us with a close up and wide photos it will potentially reduce application times as we won’t be required to visit the site.
If your project will impact your neighbour’s property by having new assets installed or relocated on or in front of their property, you’ll need their authorisation.
A single line diagram provides us with the technical information to design a connection to meet your requirements
Your accredited electrical contractor or consultant must submit a statement verifying that the installation complies with AS/NZS 61000.3.11, SA-SNZ TR IEC 61000.3.14 and Western Power’s Technical Rules.
The information allows us to check the impact of your loads on the network. You must comply with Power Quality limits as per AS/NZS 61000.3.11, SA-SNZ TR IEC 61000.3.14 and Western Power Technical Rules.
Your load breakdown allows us to assess the impact your project will have on the network. It also allows us to apply the appropriate charging policy.
Your load breakdown allows us to assess the impact your project will have on the network. It also allows us to apply the appropriate charging policy.
We’ll contact you within 10 days to discuss your application and confirm your required dates.
After our technical assessment we’ll confirm the scope of works with you.
We design the project to your needs.
After the acceptance and payment is received, we’ll schedule the works for delivery.
Your feedback is important to help ensure we’re meeting your needs and expectations.
I’ve got my site plan and site photos ready.
Apply nowEstimated time to complete: 10 minutes
If you’re not sure what you need, get advice from our team.
Talk to usWestern Power is regulated by the state government in terms of how it can earn revenue. Our revenue (through tariffs) is determined by the size of our Regulated Asset Base (RAB).
When streetlights are added to the RAB they have an economic life of 20 years. If a streetlight is replaced or upgraded to LED when it is younger than 20 years old, there’s still some value in there that we haven’t recovered back yet.
Sometimes your circumstances change and you may need to cancel or change the information within your application after you have submitted it to us.
If you wish to change the scope of work in your application we will first review the change and then either:
or
For... Read more