Medium commercial connection

If you want an electricity supply with a maximum demand greater than 250A/180kVA but no greater than 1300A/1000kVA.

How much will it cost?

We'll provide a quote

after we complete the scoping and design of your project.

How long will it take?

Up to 10 business days

to respond to your application.

After our technical assessment

we’ll contact you to discuss your requirements and work with you on an expected delivery date in line with the complexity of your project.

This is for connecting power to a property where there has never been a connection to the Western Power network before. If you simply need to reconnect an existing connection, then please speak to your retailer to set up a new account. 

What to include with your application

  • A CAD site plan

    Your CAD plan helps us better understand your work site and location of assets. We extract data from your plan to assist us with your design.

  • Site photos

    Help us understand your current connection arrangements and more easily identify potential site specific issues. Photos will need to include:

    • The extent of the worksite
    • Any obstructions in the area
  • Neighbours authority

    If your project will impact your neighbour’s property by having new assets installed or relocated on or in front of their property, you’ll need their authorisation.

  • Single line diagram

    A single line diagram provides us with the technical information to design a connection to meet your requirements

  • Statement of compliance to AS61000.3.6

    Your accredited electrical contractor or consultant must submit a statement verifying that the installation complies with AS/NZS 61000.3.11, SA-SNZ TR IEC 61000.3.14 and Western Power’s Technical Rules.

  • Disturbing loads

    The information allows us to check the impact of your loads on the network. You must comply with Power Quality limits as per AS/NZS 61000.3.11, SA-SNZ TR IEC 61000.3.14 and Western Power Technical Rules.

  • Load breakdown

    Your load breakdown allows us to assess the impact your project will have on the network. It also allows us to apply the appropriate charging policy.

  • Permission from your strata company (if applicable)

    Your load breakdown allows us to assess the impact your project will have on the network. It also allows us to apply the appropriate charging policy.

Application process

  • You've applied

    We’ll contact you within 10 days to discuss your application and confirm your required dates.

  • You'll receive a scope

    After our technical assessment we’ll confirm the scope of works with you.

  • You’ll receive design fee invoice

    We design the project to your needs.

  • You’ll receive and access quote

    After the acceptance and payment is received, we’ll schedule the works for delivery.

  • Let us know how we went

    Your feedback is important to help ensure we’re meeting your needs and expectations.

Standards, manuals and guidelines

Technical documents that provide the necessary information to enable users to comply with statutory requirements and obligations.

Design-Consultancy_bg_Image.jpg

Ready to apply?

I’ve got my site plan and site photos ready.

Apply now

Estimated time to complete: 10 minutes

Need help before applying?

If you’re not sure what you need, get advice from our team.

Talk to us

FAQs

  • What is Regulated Asset Base (RAB)
  • What if I change my mind or want to cancel my application?

Western Power is regulated by the state government in terms of how it can earn revenue. Our revenue (through tariffs) is determined by the size of our Regulated Asset Base (RAB).

When streetlights are added to the RAB they have an economic life of 20 years. If a streetlight is replaced or upgraded to LED when it is younger than 20 years old, there’s still some value in there that we haven’t recovered back yet.

Sometimes your circumstances change and you may need to cancel or change the information within your application after you have submitted it to us.

If you wish to change the scope of work in your application we will first review the change and then either:

continue the project with the variation and invoice you for any additional materials, design work and remobilisation costs incurred. We will typically only take this approach when the change is very minor.

or

 if the change is significant we will cancel your project. You will need to submit a new application with your new requirements.

For... Read more

View all FAQs