I chose to permanently remove (supply abolish) my connection when the line was transitioned to SPS, but I have changed my mind, what do I do?

You’ll need to and pay the full cost of a SPS.

We’ll honour the network connection cost for new connection applications for two years from the date the line was transitioned to SPS, if the network connection is lower than the cost of a SPS. The two-year period commences on the date the property owner is contacted by us, and is tied to the land, not the property owner. If the property is sold during this two year period, the new property owner can apply for a new connection at the lower connection cost. 

To be eligible to receive a new connection at the ‘lowest cost’ during the two-year period, you’ll need to provide all relevant documentation and planning information including, but not limited to: 

  • development plans
  • third party approvals
  • certified electrical loads