Construction of my project has not been completed; can I apply for clearance?

If construction is not required to fulfil additional requirements of your condition(s), construction does not need to be completed to obtain clearance – for example, access into an existing pillar. You need to have accepted and paid the quote for clearance to be provided.

Where construction of your project is required to fulfil requirements of your condition(s) you need to wait until construction has been completed to progress.