Medium commercial electricity supply
Approximate time required to complete application: 10 minutes.
Use this form if you want an electricity supply with a maximum demand greater than 250A/180kVA but no greater than 1300A/1000kVA.
Design complexity | Definition | Time |
---|---|---|
Standard design |
Small and single site installations, changes and relocations; low voltage network only, no 3rd party approvals |
21 days |
Detailed design |
Multi-site installations and relocations; environmental, safe excavation, EPR, 3rd party negotiations and approvals required, overhead network works required. This includes all high voltage (HV) work |
45 days |
Complex design |
Significant asset relocations, network augmentations and substation upgrades, transmission zone substation impacts and 3rd party negotiations and approvals required |
Complex design timeframes vary. Your designer will contact you to discuss your project. |
Electricity connections can be varied and complex. We recommend that a professional electrical consultant or contractor completes this application.
You'll need to the following to submit an application:
Approximate time required to complete application: 10 minutes.