Smart grid
Powerlines and substation projects
- Powerline projects
- Ellenbrook underground power project
- Powering Perth's Communities
- Guildford to Southern terminal transmission line
- Hopeland transmission line
- Kemerton to Binningup transmission line
- Kojonup to Albany transmission line
- Mid West Energy Project
- Muja to Wellstead transmission line
- Northern Terminal to Hadfields transmission line
- Automation works
- Bunbury-Busselton-Margaret River Project Suite
- Ellenbrook underground power project
- Substation projects
- Balcatta substation
- Baldivis substation
- Bayswater substation
- Collier substation
- Cottesloe substation upgrade
- Forrestdale zone substation site
- Furnissdale substation land acquisition
- Geraldton Port and CBD Power Requirements Project
- Hocking substation land acquisition
- Joondanna zone substation
- Maddington substation
- Manning Street substation upgrade
- Melville and Fremantle power options
- Morley substation
- Mundaring Weir substation
- PTA Sutherland Substation Cable Supply Project
- Sawyers Valley substation upgrade
- South East Terminal substation
- Western Terminal Reinforcement Project
- Balcatta substation
- About substations
- Site selection process
- Community concerns
- Project archive
- Powerline projects
Underground power
Helicopter line maintenance
Wood poles
Medical Centre 66/11 kv zone substation
Zone substation expansion and distribution network upgrade

The QEII Medical Centre (Sir Charles Gairdner Hospital), presently connected to Medical Centre Zone Substation, is in the process of a major upgrade. This upgrade will increase the load from 12.5 MVA to 23 MVA in 2015 then 27.5 MVA by 2020. This load increase is driving a customer-driven project to upgrade the Medical Centre substation to 11 kV by June 2014.
A new 66/11 kV substation will be constructed on land adjacent to the existing 66/6.6 kV substation. The substation will be constructed to an N-1 standard due to the essential services that the medical centre provides. This element of the project has an estimated cost of $30 million.
The current options for the new 66/11 kV substation are outline below.
- Replacing the existing zone substation with 3 x 33 MVA zone substation.
- Replacing the existing zone substation with a 2 x 66 MVA zone substation.
Either option that is selected will be operated at 66 kV and then operated at 132 kV in the future.
The target completion date for the Medical Centre Zone substation expansion is June 2014 to meet the QEII requirement and to integrate with Western Power’s wider network investment strategy in the area.




