Skip Navigation

Powering Perth's Communities

Western Power has adopted a fresh approach to the Eastern Terminal project. The new project will be known as Powering Perth's Communities (PPC), reflecting that this project will deliver benefits to the entire Perth community, including the Hills area.

Phase I of the PPC project involves the direct tie-in of a new 330 kV line at Hacketts Gully to bring an additional 1000 MW of power from generators in the south to the Perth metropolitan area by 2011. The new line, running from Shotts Terminal (near Collie) via Wells Terminal (near Boddington) will connect to existing lines at Hacketts Gully.

Phase I is drawing to a close with the announcement of the chosen tie-in option on 30 January 2009. Western Power will begin consulting with the broader Perth community on Phase II in the coming months.


What is Phase II of the new project?

Latest news

Western Power would like to announce that Option 1, which involves installing a gantry and extra single pole at the intersection of Mundaring Weir and Bahen Roads in Hacketts Gully, will be used to link a new major power line to the existing grid.

In coming to this decision, Western Power considered the social, environmental, technical and economic issues as well as the recommendations from the Focus Group meeting held in November 2008. The decision is discussed in detail in the 'Powering Perth's Communities Phase I - Outcomes Summary' document (available for download below).

The Focus Group, while not endorsing the project, confirmed that it preferred two possible options for connecting the lines. These were Option 6A and Option 1, with preference for Option 6A. The two options are the same except that an existing tower would be replaced with a similar height pole in Option 6A.

When reviewing the two options comparatively Western Power found that Option 6A had a greater impact with regard to safety, cost, risk to power supplies, risk of traffic interruption during work and land clearing. For these reasons Western Power determined that Option 1 was the preferred tie-in solution.

In addition to the community consultation, Western Power will be submitting Regulatory Test and New Facilities Investment Test (NFIT) applications for determination by the Economic Regulatory Authority (ERA) for this project.  These tests consider the technical and economic implications of a number of alternatives to ensure that the most economically efficient alternative is adopted.  The applications will be based on the South West 330 kV Bulk Transmission Reinforcement - Discussion Paper and will consider submissions made to Western Power forthcoming from our Invitation for submissions - Proposed 330 kV South West Transmission Reinforcement which was open for industry comment from 17 December 2008 to 9 January 2009.

An environmental and social review of the transmission line routes associated with the two main transmission line route alternatives outlined in this discussion paper has also been undertaken (available for download below).

Subject to Regulatory Test and NFIT approval, the next stage in this project will be the construction of the new transmission line between Wells Terminal and Hacketts Gully which is planned to commence in late 2009, at the southern end, with the tie-in works in Hacketts Gully scheduled to be completed in late 2011.

In addition, Western Power will begin consulting with the wider Perth community on Phase II of the PPC project to examine ways to connect the new line into a new or existing switchyard when required in the future.

 

Downloads

News archive

Community Focus Group outcomes

Community Interest Group presentations

Focus Group formed

A fresh start

Project Information

To ensure sufficient power is available in the network and that the security of the network is not compromised, two critical components of the Powering Perth’s Communities project were identified.

1. A requirement to deliver an additional 1000 MW of power to the network by 2011 via a reconstructed 330kV line from the southwest to Hackett’s Gully in the Perth Hills in conjunction with the development of South Eastern Terminal (near Byford), and
2. The ability to connect this line to a new or existing switchyard by 2017, or possibly earlier.

The security of the electricity network is reliant on the new 330 kV power line connecting to a new or existing switchyard by 2017. Switchyards enable Western Power to connect and isolate powerlines, maximising the security of the network.

This means a more secure power supply for Perth's communities, including our hospitals, schools, businesses and your home.

To meet current electricity demands, a tie-in solution will be sufficient in the short term. However, to meet the future predicted increase in electricity demand, this new line will need to be directly connected into a switchyard.

Western Power is undertaking the Powering Perth's Communities project in two phases.

  • Phase One will begin construction of the new transmission line between Wells Terminal and Hacketts Gully in late 2009, at the southern end, with the tie-in works in Hacketts Gully scheduled to be completed in late 2011.
  • Phase Two will involve securing the network by connecting the new line into a switchyard (either new or existing), noting however that the Eastern Terminal switchyard proposal is just one of options to be investigated.

Each phase will involve working in collaboration with the community to review and evaluate the available options using a sustainability assessment taking into account community values and concerns as well as technical requirements.

Phase I Click for more information

Phase II Click for more information

Working with you

The Powering Perth's Communities project represents an opportunity for Western Power to apply a sustainability assessment approach to decision-making to ensure the project achieves the best balance of outcomes for society, the environment, the technical requirements and the most efficient use of funds. In doing so, Western Power looks to involve the community more fully in the process.

Western Power looks forward to working with the community on this project.

Contact us

For more information please contact ppc@westernpower.com.au or call (08) 9326 4007

Subscribe to Projects RSS Feed

To view PDF files you will need Adobe Acrobat Reader.

Customers with accessibility issues.

Page update on 30 January 2009