Kemerton to Binningup transmission line

In brief

  • Western Power is currently investigating line route options to provide electricity for Water Corporation's proposed desalination plant in Binningup.
  • The proposed desalination plant will require a power supply of 132kV from Western Power's Kemerton terminal yard.

Proposed timeline*

August 2008 Fauna expert to assess birdlife
Proposed line route announced
Spring 2008 Flora and fauna survey
November 2009 Construction commences
June 2010 Line commissioned
June 2011 Substation/Desalination plant at full capacity

* subject to change

Consultation

Western Power has been consulting with landowners affected by the 10km line and new substation since April 2008.

The most recent consultation session was held at Binningup on Tuesday July 8.

Western Power has met with land owners and key stakeholders to hear their concerns and provide advice about the project.

Environment

Western Power has appointed a fauna expert to provide advice on how to minimise the impact on local wildlife, particularly birds.

The proposed line route and the substation will undergo a flora and fauna survey in spring to minimise the impact of the project on the species endemic to the area.

Line route

The new line will run 10km north-west from the current Kemerton terminal substation to a new substation to be constructed at Binningup within the Water Corporation's new desalination plant.

Western Power will finalise the line route once environmental impact studies are complete and community concerns have been addressed.

The new 132kV single circuit transmission line will be constructed using steel poles.

Contact us

For more information please contact Project Officer Matt Pollexfen on (08) 9326 4684.