Skip Navigation

Joondalup substation

As part of its commitment to improve the quality and reliability of the power supply and to cater for the future power needs in your area, Western Power plans to construct a new zone substation in Joondalup.

Western Power plans to establish a 132,000 volt (132 kV) zone substation on Lot 2 Shenton Avenue, Joondalup.

The substation is required to meet the increasing demand for power as a result of growth in the City of Joondalup and increased electricity use. The substation will improve the reliability of power supply and allow for future growth in the area.

The project will include the installation of a single transformer, a portable building to house the essential substation switching equipment and other electrical equipment for the substation.

The substation will be connected to the existing Mullaloo to Wanneroo 132 kV transmission line, which traverses the substation site.

Traffic disruptions

There may be traffic delays in the area while equipment and materials are transported to the substation site. Western Power and its contractors will endeavour to minimise the disruption and safely manage traffic flow in the area.

Project updates

Location

Joondalup Substation location

Proposed timeline*

 March 2009 Site works
 April 2009 Construction commences
February 2010 Landscaping works
April 2010 Project completion

* subject to change

Contact Us

More information on this project please contact Western Power’s Project Officer, Simon Collins on (08) 9326 6502.

Subscribe to Projects RSS Feed

To view PDF files you will need Adobe Acrobat Reader.

Customers with accessibility issues.

Page update on 26 November 2008