The Boddington Gold Mine Management Company (BGMMCo) Ltd has applied for access to Western Power’s transmission network to receive additional power for the Boddington Gold Mine Expansion Project.
Situated 120 km south of Perth, the Boddington Gold Mine closed in 2001 pending planning approval for the expansion project. The mine will be fully operational by September 2008.
The existing 132kV transmission line supplying the Boddington area does not have sufficient capacity to meet the increasing needs of the mine, so significant network reinforcements are required.
Western Power advises walkers in the Boddington area to watch out for construction vehicles and to exercise caution when crossing powerline corridors on the Bibbulmun Track. For further information about this project, please contact Kelly Freeman on 9326 4500.
Subject to line route and substation site selection and approvals
| January 2006 – November 2006 | Line design |
| April 2006 – June 2007 | Substation design |
| April 2006 – February 2008 | Procurement |
| March 2007 – September 2008 | Line construction |
| March 2007 – July 2008 | Substation construction |
| September 2008 | Project completion |
Please visit the Boddington Gold Mine website.
For more information, please contact Project Officer Matt Pollexfen on 9326 4684.
For more information regarding Boddington Gold Mine Management Company (BGMMCo) please visit their website.
Last updated 22/7/2008