All network charges will be charged to the person making the application for service. Network charges as at 01/04/2009 for standard supply. (See end note for standard supply definition)
Some services/fees attract GST.
| Purpose | Service | Charges | GST |
|---|---|---|---|
| Customer connection | To provide an overhead service or upgrade to customer point of supply or connect underground consumer main (up to 63 amp) |
$272.00 |
No GST |
| Supply disconnect/ reconnect | Disconnection/reconnection of overhead service leads or underground consumer mains at the customer request (up to 63 amp) |
$250.00 |
+ GST |
| Upgrade of underground service | Single-phase – 1 |
$227.00 |
No GST |
| Temporary builders supply – overhead | Single-phase – 1 |
$300.00 |
+ GST |
| Temporary builders supply – overhead | Three-phase – 3 |
$600.00 |
+ GST |
| Pole to pillar |
Subsidised cost up to three dwellings per lot * Further conditions apply: Please refer to the Residential Connections section for more details on whether your connection is eligible for this subsidised rate. |
One dwelling $681.00* Two dwellings $1362.00 |
No GST |
| Project cancellation | May be charged if project is changed by customer Administration charge - Cancellation or scope change prior to commencement of construction plus design cost incurred |
$550.00 plus design costs |
+ GST |
| An administration charge may be charged if job is cancelled or scope change after construction commenced plus costs incurred on project prior to cancellation or scope change |
$550.00 plus costs incurred |
+ GST on admin only | |
| Western Australian Planning Commissin | WAPC amendment to previously cleared plan |
$58.00 |
+ GST |
| WAPC incorrect/insufficient detail provided to enable clearance |
$115.00 |
+ GST | |
| Underground distribution schemes & Subdivision charges | Feasibility Enquiry Feasibility Study |
$315.00 |
+ GST |
| Design information package |
$495.00 |
+ GST | |
| Charge for bonds/clearances (pre 1st July 2007) Per Lot Fee (PDF 28kb) |
$363.00 |
+ GST | |
| Design conformance review per stage Plus Variable Charge |
$363.00 $38.50 |
+ GST | |
| Variable charge per lot | $5.50 |
+ GST | |
| Design re-conformance review per stage Plus Variable Charge |
$242.00 $27.50 |
+ GST | |
| Quality assurance | $959.00 | No GST | |
| Variable charge residential lot | $5.00 | No GST | |
| Variable charge commercial/industrial per metre of trench | $0.71 | No GST | |
| Part payment arrangement | Administration fee will be charged for changes by the customer to the normal payment scheme offered | $550.00 |
+ GST |
Note: Western Powers standard supply is up to: