Primary producers
To apply for a new connection as a primary producer you must be recognised as a primary producer by the Australian Taxation Office.
How to apply
- consult an electrical contractor to:
- determine your electricity needs - An electrical contractor can help you wil this
- help complete the online design and quotation application form - once the connection has been established you will need to set up an account with an electricity retailers
Note: We cannot guarantee that three-phase power will be available to your site, especially in rural or more remote regions.
How much will it cost?
Connections are assessed and quoted on a case-by-case basis. Additional charges may be incurred in the following instances:
| Type of fee | Service | Cost |
|---|---|---|
| Part payment arrangement fee | Charged for changes made by the customer to the normal payment scheme offered. | $550 (inc GST) |
| Project cancellation fee | Charged if the customer cancels or changes the job before construction starts and/or if any design costs are incurred. | $550 (inc GST) plus design costs |
| Administration fee | An administration fee may also be charged if the job is cancelled or changes are made after construction starts and/or any costs are incurred prior to cancellation or scope change. | $550 plus costs incurred (GST inc on admin only) |
For more information
Contact our customer services centre on 13 10 87 or enquiry@westernpower.com.au.
Related links
- Western Australian distribution connections manual
- Land developers & designers
- Applications and queuing policy (appendix 7)